Hello!
We have a project request from with required project categories. The Project categories already have a dependent field asking specific questions based on the project category selection.
We then have a “desired due date” field where the requestor can select the desired due date of their request.
Issue: Each Project has a realistic time period to complete. For Example, New Collateral is 2 weeks, Collateral Edits is 3 days. This is not a field in the form, just note included on the name of each Project.
What we are tying to solve for: We would like the “Desired Due Date” calendar to be restricted to only show dates beyond the " realistic time period to complete". For Example, if someone selects New Collateral as their Project type, we want the Desired Due Date calendar to only show dates 2 weeks out from todays date.
Is there a way to do this?
Thanks!
-Chris