Hello,
I would like to know if it’s possible to add or remove a project from a task when the task is added or removed from a section ?
If it’s possible what is the best way to do it ?
Thx
Hello,
I would like to know if it’s possible to add or remove a project from a task when the task is added or removed from a section ?
If it’s possible what is the best way to do it ?
Thx
Welcome, @p4ul,
Yes, if you’re on Asana Business or Enterprise you can create a custom rule where the trigger is Task added to a section and the action is either Create new project from task or Move task to a project (which will add the project to a task = multi-home task).
Larry