Briefly describe (1-2 sentences) the Bug you’re experiencing:
I created a template with a 10 day period (no weekend days) and put Start/End dates in the progress menu… When using the template with a start date of Monday or Tuesday, the due dates populate correctly on all the tasks within… When starting on a Wed, Thursday or Friday - it goes to an 8 day work period and dates are incorrect… I make sure that the ‘assign’ tasks on weekends’ tab is unchecked when using it to create a new project.
Steps to reproduce:
- Make a template with a 10 day work period, assign start/end dates in progress tab. No weekend work.
- Use the template to make a new project and try starting on a Wed, Thurs or Friday. No weekend work.
Browser version:
Chrome
Upload screenshots below:
WednesdayStart|344x500 !