Is it possible to see subtask dependencies in Timeline view?
Hi @anon97145220, welcome to the Community Forum and thanks for reaching out!
In order to see subtask dependencies in Timeline view, you’ll need to add the subtasks to the project
I hope this helps, let me know if you have any questions!
To follow up on what @Emily_Roman mentioned:
Be aware, adding a subtask to the parent-level project will also add them to the main task list of your project as well.
So, if you want a clean task list that isn’t mucked up by all of your subtasks everywhere, you’ll want to avoid adding them to the parent project and give up having them on the Workload or Timeline views.
I do not foresee them being able to resolve this issue soon as it appears to be a major limitation of the way the platform was fundamentally engineered from the get go.