Hi,
I have a question whether it is possible to create a rule that when all tasks in a section are complete the whole section is moved to another section within the same board.
Hi,
I have a question whether it is possible to create a rule that when all tasks in a section are complete the whole section is moved to another section within the same board.
Hey @Paulien_Illy,
Just to clarify you want the completed tasks within that section to move to another section when they are all completed? Or you want to have a section inside a section ?
There is a rule that when a task is complete it moves to another section but if you need to wait for all the tasks to be completed to then move i’m not sure how you would approach that.
Hi Danielle, I meant indeed the latter. I want all tasks within one section to be marked as complete to be then moved to another section that I called ‘done’. This so I can still keep track of all the tasks within a project before its moved in its entirety to the ‘done’ section
Ah okay, unfortunately rules cannot apply to sections in this way it would have to be one by one or there needs to be a trigger point
I’m not sure if the following idea meets the need, but you never know
If you create a relationship like this between tasks A, B, C, D:
Then you can create a rule that says :
And so in this case, you validate only the milestone D, and that validates and moves A, B and C automatically.
Julien
Hello! I have a question about the first use case that Danielle-GenD outlined! Currently, my project has 4 sections:
In Progress
On Hold
Pending
Completed
I clicked the lightening bolt next to the ‘In Progress’ section header, and added a rule that All tasks marked ‘Completed’ will be moved to the Section = Completed
When I clicked out, it showed that the rule had only been applied to the ‘Completed’ section (i.e. it only shows up when I click the lightening bolt next to the ‘Completed’ section header)
It also says the rule is active, but has not been run. Is this because going forward, the rule will only affect tasks that are now clicked completed? Is there a way to automatically move all of the old completed tasks in the ‘In Progress’ / ‘Pending’ / ‘On Hold’ section into that Completed section? And do I need to apply the rule to each of these sections, or will it automatically be applied to all the tasks within the project, regardless of their section?