Hello!
I’m trying to add rules to several sections in sequential order that do this:
When task marked complete, move task to the next section
Mark task incomplete
Assign task
My issue is that when the rule of marking a task complete is run, Asana doesn’t know which section to move the task to.
How can I create the condition for moving the tasks through the sections in the correct order?
TIA!!
lpb
20 September 2022 18:48
2
Welcome, @Lilly_Pet ,
I think you need to have a rule for each section, and each needs to be a multi-condition trigger:
Click the “+” sign within the trigger to make your trigger have a pair of conditions:
Tasked marked complete
Task moved to (read as “task is in”) section
This will let you target each rule to a section.
Hope that helps,
Larry
2 Likes
Thank you, Larry - much appreciated!
1 Like
@Lilly_Pet This is super-easy and stuff I do all the time with our rules set-up. If you’re still struggling, please DM me (jennifer@siddhicapital.co ). I’ll show you how (screenshare).
Jennifer
lpb
26 September 2022 18:34
5
@anon12986944 , You replied to me but maybe you meant @Lilly_Pet ? I think my solution provides the approach unless you suggest another direction?
Thanks,
Larry
@Lilly_Pet This is super-easy and stuff I do all the time with our rules set-up. If you’re still struggling, please DM me (jennifer@siddhicapital.co ). I’ll show you how (screenshare).
Jennifer
@lpb Oops, sorry. Yes, I think your solution does take care of it. I was only offering to help if there are continued issues. -Jennifer
1 Like
This topic was automatically closed after 6 days. New replies are no longer allowed.