Rule to move task to column when marked complete hides the task

We’ve got a project space called Tech Requests where the rules are:

  1. Mark task as complete when moved to “Done” section, and
  2. Move task to “Done” section when marked complete

The problem is, if we mark a task as complete, we don’t see the task in the Done section at all, whether in a Board or List view - it just disappears.

Steps to reproduce:

  1. Create task.
  2. Mark as complete.
  3. Task disappears into the abyss (it is searchable, though we can’t see the stack of completed tasks in the project space)

Browser version: Chrome Version 105.0.5195.126 (Official Build) (64-bit)

Upload screenshots below:

Hi @Peter_Kim,

Answer: those tasks are being hidden by your view filter which is set to only show Incomplete tasks:

1 Like

This topic was automatically closed after 7 days. New replies are no longer allowed.