Question about Auto-shifting dates for dependent tasks

Thanks @anon5798578

When we move the task to a later date the dependent task moves. However, when i move it to an earlier date, the dependent task doesn’t move flawlessly.

What works: My Task 1 finishes on Thursday Nov 5. Task 2 (dependent on Task 1) begins on Friday Nov 6. Now if I move the Task 1 to Next week Wednesday Nov 11, Task 2 automatically moves to Thursday Nov 12.

What doesn’t work: After above step, now if I move the Task 1 back to Nov 5, Task 2 moves to Monday Nov 9, instead of Friday Nov 6.

This looks like some kind of bug.

1 Like

Hi @anon41024217, thanks for reaching out! I’ve moved your post to a separate thread so we can investigate this further.

This seems to be related to the fact the Auto-shifting dates for dependent tasks feature doesn’t currently support weekends. Just to confirm, how are you moving the tasks in Timeline view? For example, are you multi-selecting both tasks or are you moving them one by one?

2 Likes

Hi @Emily_Roman, thanks for the prompt response.
I was moving just one task at a time and checking if the dependent task moves along with it. I wasn’t using it on a live project yet, I was only testing out the functionality before I can show it to my team.

@anon41024217
Actually in Asana’s auto-shifting capability, in this scenario, Task 2 would not move at all when you move Task 1 back to Nov. 5. Asana only moves dependent tasks when you move a precedent and that move creates a date conflict (overlap) between the precedent and its dependent.

So I’m not sure why Task 2 moved to Nov. 9 (or again, moved at all). Are there other tasks in the project, or other dependencies on Task 1 or Task 2?

Hi @Phil_Seeman, it seems you are right. I tried again and Task 2 did not relatively move at all.
However, in timeline, this should still be possible. The dependent task should move back to the date right after the principal task, unless the resource is already assigned another task on that date. Timeline should ideally work like a Gantt chart.

Another important feature missing is that the timeline should show sub-tasks. Sub-tasks that cannot have start date or due date, beyond the start/due-date of the parent task. This is missing too.

Yeah, Asana just doesn’t work that way at present; they chose to only shift dependents when there is a date conflict.

If you want the more universal behavior, the Auto-Adjust Workflow type of my Flowsana integration will do exactly that - it shifts dependents in all cases, regardless of whether there is a conflict situation or not. (It also works in all views, not just Timeline view.)


This is a very popular request; you can add your vote for it here:

4 Likes

Hi,

Is the auto-shifting of dependency conflicts available in a Business Trial? We are trialing Asna and I wish to use this capability but it is not working for me and I would like to understand why.

Thank you!

It is - the trial has the same features as the paid subscription.

Make sure you read this section carefully to understand how it works:

In particular, note that for auto-shifting to occur, (1) you must be in the timeline view, and (2) the predecessor task must overlap the dependent task after you’ve moved that predecessor.

1 Like

Thanks for your response Phil!

I am curious to understand if the appropriate way to see these auto-shifts is to add start dates for tasks, so that the system can 1). detect the overlap, and then 2). perform the auto-shift?

It’s hard to say definitively how that would alter the auto-shift behavior in your case; it really just depends on the specifics of your scenario. Really the only way to answer a specific auto-shift-behavior question is to have specific examples like Vaibhav provided above. (Screenshots of the Timeline view are even better for helping us to visualize what’s going on :slight_smile: )

1 Like

This topic was automatically closed after 4 days. New replies are no longer allowed.