Changing all the dates of a project

Yes, @Jason_Woods, thanks for the mention!

Hi @Derek_AM - are your project tasks constructed with dependencies? If so, the Auto-Adjust workflow type of my Flowsana integration can help you. If you change the date of a task with dependent tasks, Flowsana will automatically shift the dates of all of its dependent tasks by the same number of days (and this will flow down through a chain of dependencies).