Is there a way to set up an automation that would trigger a project status update based on the status of tasks/due dates? For example, if a task is overdue, the project status would automatically be updated to “at risk” or “off track”.
Hi @Sarah_Cavanaugh , currently, this is not natively possible to do within Asana using Rules.
I was thinking perhaps a 3rd party integration could do this via the API but according to @Bastien_Siebman’s awesome post, it doesn’t seem this is supported.