Automatically update project status

Hi there,

Is there a way to set up an automation that would trigger a project status update based on the status of tasks/due dates? For example, if a task is overdue, the project status would automatically be updated to “at risk” or “off track”.

Thanks!

Hi @Sarah_Cavanaugh , currently, this is not natively possible to do within Asana using Rules.

I was thinking perhaps a 3rd party integration could do this via the API but according to @Bastien_Siebman’s awesome post, it doesn’t seem this is supported.

pinging the API experts in case this could be custom coded… @Bastien_Siebman , @Phil_Seeman , @lpb

Welcome, @Sarah_Cavanaugh, and thanks, @Richard_Sather,

It appears that make.com, at least, could do this:

This also could be custom-coded with the Asana API.

Thanks,

Larry

This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.