Briefly describe (1-2 sentences) the Bug you’re experiencing:
The workload view does not show “hours per week”. It spreads effort evenly from start to end dates.
I would like to estimate hours of work per week. For example: Social media post writing is 8 hours per week and social media monitoring is 4 hours per week. Start date is October 1, end date is October 31. I should see 12 hours of effort every week (about 51 for the month) when I use the workload view.
Steps to reproduce:
Create a project.
Add a custom field “hours per week” that is a number.
Add a task starting now and lasting one week. Assign it to someone. Add 25 in the “hours per week” field.
Add a task starting immediately after and lasting two weeks. Add 50 in the “hours per week”.
Create a portfolio and add the project.
Go to workload view.
You will see that the person is tasked with 25 hours worth of effort for all three weeks.
Browser version:
MacOS app
What version of Asana are you using (Basic/Premium/Business/Enterprise)?
Business
Upload screenshots below:
Screenshot shows and example where I assigned myself 50 hours/week for a 1 week task, 50 hours/wk for a two week task, 25 hours/week for a one week task.