Is there a way to do this? or does it have to be manual?
I think if subtasks are specifically included in the dependency chain as well then they could participate.
Thanks,
Larry
After seeing this, I checked out the dependencies of the subtasks, and they are included in the dependency chain. I could send some screen shots if you’d like to verify. My dependency management options are set to Maintain Buffer and ignore weekend awareness…
Thank you for looking at this.
Note: Not a solution but marked as such to elevate a key reply
Interesting. If you think it’s not working as described in New Auto-shifting Dates for Dependent Tasks in All Views | Asana Product Guide • Asana Product Guide, then I think you should either post in Report a Bug or email support@asana.com so they can have a look.
Thanks,
Larry
Thanks Larry. I’ll do both.
This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.