Hi, I have setup a task which repeats every week and then I have created subtask to a team member which is also repeats. When I complete the main task and when my team completes their subtask it is duplicating the subtask?
Welcome, @Meagan_Hungerford,
I’m afraid that unpredictable results are expected when you have a repeating subtask within a repeating parent task. You must only have one or the other. So perhaps you can separate these to avoid the known issues.
Thanks,
Larry
1 Like
This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.