I am also trying to find a solution. I have created a form request in jotform (it’s more robust than the Asana form feature). The integration is so seamless except one (huge) thing. I have a formula in jotform that copies my “start date” and “end date” into a field. Ideally this field should just copy and paste into the “due date” field in Asana. But it will only take the start date.
For example:
Jotform field START DATE: 1/1/2021
Jotform field END DATE: 12/31/2021
Jotform formulate field DATE RANGE: 1/1/2021-12/31/2021
Asana will only take “1/1/2021” but if I manually copy and paste the entire date range “1/1/2021-12/31/2021” will import fine. However the integration does not correctly do this.
Currently the only manual work around I can do is redirect the ASANA DUE DATE field to be linked to the jotform END DATE field because of what i need, the END DATE will allow my rule to run. But I have to manually go and enter the start date for every new request.