Imported CSV Task Order is reversed on timeline (before dates entered)

Task order is reversed on the timeline vs my csv task list, which makes setting dependencies very challenging. This means that I have to re-order the entire project one by one on the timeline which largely defeats the functionality of the import function. Interestingly, the list view is in the correct order but the timeline is not.
Note that I do not have dates to import, just task durations, so as I build the dependencies on the timeline, I’m adding durations there by dragging out to the right number of days. The specific dates don’t matter, but the duration does.

Did you consider “simply” reversing your CSV file before importing. I understand this is a workaround, but it could solve your issue for now.