Hi there,
I am wondering if I am able to copy and paste the below tasks into the same board?
Would someone be able to help me?
Thanks,
Andrew
If you want to not duplicate tasks one by one I suggest:
- creating a dummy project
- multi select the tasks
multi-home them in the project (not move them, multi-home them)
- duplicate the dummy project
- delete the dummy project
- move the tasks out of the 2nd dummy project
- delete the 2nd dummy project

Thanks Bastien, that’s perfect 