Dynamic Parent Task Due Dates

Hi everyone :waving_hand:

Great news: Subtask Date Rollups are now live in Asana! :tada: Thank you to everyone who requested this and shared your feedback here. It really helped shape the feature.

With a rollup, a parent task’s start date moves to the earliest subtask start date and its due date to the latest subtask due date. You can roll up a single parent task or a whole project at once, and nested subtasks are included too.

Just a heads-up that rollups are manual (run them again if subtask dates change) and they only update dates already set on the parent. Project-wide rollups can’t be undone, so double-check before confirming.

Give it a try and let us know what you think! :speech_balloon: