Due Date Approaching Rule Doesn't Seem to Work

Important note: To help us resolve your issue as quickly as possible, please ensure to fill out all the sections below. Do not share any private information such as email addresses or phone numbers - This is a public Forum!


Briefly describe (1-2 sentences) the Bug you’re experiencing:
I have a rule set up in My Tasks for when a due date is approaching by 1 week to move the task to a board section called Active. I would expect that when a task due date is equal to or less than 1 week the rule would run at midnight or soon after and move the task. It has yet to run at all after nearly a week and numerous tasks falling into that category.

Steps to reproduce:
Create a custom rule that triggers on due date approaching with action to move to a section.

Browser version:
Microsoft Edge Version 114.0.1823.51 (Official build) (64-bit)

What version of Asana are you using (Basic/Premium/Business/Enterprise)?
Business Trial

Upload screenshots below:
image

Asana does not match on the “or less than” part of your statement. If you specify “in one week”, it only fires if a task is exactly one week out at midnight when the rule is evaluated.

(If you want the “1 week or less” behavior, you can use our Flowsana integration - our date rules do implement the “or less than” part of the behavior you’re looking for :wink: ).

2 Likes

Thanks! I will check out Flowsana.

FYI I moved this to the Tips and Tricks forum section as it’s expected Asana behavior and not a bug.

1 Like