Dates tracking

We are trying to use asana as project management tool and dates tracking is vitally important.
Does anybody have ideas on how to:

  • compare actual task finish date with initial due date
  • see task actual completion date (status changed to complete)
  • compare planned task duration vs actual task duration
  • measure SLA (tasks completed in time vs all tasks completed)
  • get report about tasks that were finished with breaking initial due date

What I can think of is to have additional field of date which can be used as initial due and which is protected from changes. But as far as I know there is no option to add such field.

Any tip on that?
Thanks!

Hi @Anton_Maslov :wave:t3:

Some of this might be achievable via the Asana Advanced Search, but I would also recommend checking out time-tracking third-party integrations: Asana Apps and Integrations • Asana

Hope this helps, but let me know if you have any follow-up questions!

@Anton_Maslov, With advanced search and using Asana2Go (free to most users/companies) Interactive Tables, you can see the five Asana date fields (including Date Completed) and whatever custom fields you have, all in a sortable list view. This might help address some of your needs. (Disclaimer: I’m the creator.) More info:

Larry