Date Range Option Not Showing Up

Hi there,

I am having some trouble with the tasks in one of my projects. The option to add a date range is only showing up in some tasks, but not others. Do I need to remake all of the tasks that aren’t working or is there a setting I accidentally messed up?

Thanks!

2 Likes

@anon39970498, Is there any chance some tasks are Milestones? Those can only have a Due date. Or, since Start date is a Premium feature, is there any chance some tasks are multi-homed to projects that are part of a Premium Team and some are not?

Hope that helps,

Larry

5 Likes

Ah! Yes, they are milestones! That clears that up. Thank you so much!