Hi,
Here’s the scenario:
a task is multihomed in two projects, and in each one it has different other tasks linked with dependencies. When the main task is rescheduled while looking at the project A, only the dependent tasks in project A shift properly, while the tasks in project B stand still, causing an overlap.
Why don’t all dependent task move, regardless of which project am i viewing? It doesn’t make sense.
Yes, i know i might create a big project with all the dependent task in there, but it’s not feasible in my case and it’s a workaround, not a solution.
Thank you and regards