Unable to assign multiple task on Timeline view

Hi all!

I used to be able to move a task and assign it to someone by moving the task in the timeline view. Recently I cannot. When I move the task, the date turn red. There is no dependencies.

Can someone help me with that ? I guess that is a easy fix but I can’t find..

Thanks a lot !

Hey there, I know this is frustrating. Timeline drag behavior depends on how the view is set up, so a quick check usually fixes it.

In Timeline, set Group by to Assignee. Then drag the task vertically into the other person’s lane to reassign. If you’re not grouped by Assignee, dragging only changes dates, which is why the bar turns red when you move it.