"Maintain Dependencies" no longer an option in Timeline View

Dependent tasks on the timeline no longer move when the master task is moved. No longer have the option to maintain dependencies on the timeline view. This was a key feature of this tool. Where it used to allow me to adjust dependency settings under timeline dependency settings, it now only allows to me to highlight the critical path. This is totally useless.

Is anyone else seeing this? I’m not sure how we are supposed to manage projects if all of the dependencies between tasks (not subtasks) in the templates we have built out are unable to be adjusted.

Hi @Erin_Gough , and welcome back to the Forum!
I noticed the same problem today, and I have flagged this as a bug! I hope this is something that can be fixed really soon. Thank you for highlighting the problem!

Hi @Erin_Gough
Please click on the drop-down menu next to your project’s name, then select Edit Project Settings, and Dependencies.
You should be able to edit the dependency settings following that click path.

I hope this helps!

Sneaky! That did work though thank you