I am trying to create a bundle with 3 sections, each with 3 tasks. When I apply the bundle however, I only see 3 empty sections, 0 tasks. Can someone please help
Welcome, @Bree_McManus,
Bundles don’t contain tasks (only Sections, Fields, Rules, etc.) so when you apply a bundle with additional sections, the sections will be added to the projects but will always be empty until you adjust each project individually if you need to move existing tasks there.
Thanks,
Larry
Thank you for your reply. Is there another feature in Asana that can manage this? I have attempted something similar with project templates but when changes are made to the template, these do not update on already published projects, so I am trying to find a solution
I’m not sure what the underlying need is, so if you could briefly describe the workflow you have and the particular use case that you want to address, that might allow us to look at the problem holistically in order to give you the best reply.
Hi @Bree_McManus , as @lpb said, it would be great to provide a bit more detail but I have a feeling that you need to make sure your Bundle is also added to your template.