I created a task that is blocked by other tasks. A user was able to mark the task complete by moving the task to a section with a rule that marks tasks complete. Is this the expected behavior?
Example:
- Task A is blocked by Task B, which is not marked complete.
- User moves Task A from New to Complete, which has a rule to mark tasks complete when they’re moved to Complete
- Task A shows as still blocked by Task B, but is marked complete.