I’m a little confused about how this works or how I should set up to work better: I have a project with a task, priority listed as “medium.” That task, when it appears on “My Tasks” does NOT have a priority listed. They both have priority fields…why don’t they map over from one to another? Is there a way to make them connected?
Chrissy, Can you confirm if both the project and your My Tasks are using a “library” defined field? In order to share values across projects, my understanding is that they should be defined as a shared library field, instead of a “locally” defined field in the project. This is my experience anyways! ~jenn
To know if you are using the same field, there is an easy test: open a task assigned to you that also belongs to the project → if you see 2 “Priority” fields in the task pane on the right, then you did not choose a field in the library but instead created 2 fields. Let us know!