Task due dates not calculating correctly when project is created from the template.

Context: A cross-functional team of 30+ stakeholders works within a portfolio of projects that all have the same exact tasks being performed each project, with the calendar dates typically being the only difference between them. I built a template that captures all of their task details and worked with each stakeholder to establish which “week before opening” each task needs to be performed. That WBO custom field is adjacent to the due date field and within our template, then added the 7x (days) calc to the due date as “X days before”. There are approximately 500 tasks within the template and each project created.
Example:
project due date: 6/3/27
an example task needs to be completed 22wbo (ie 154 days before)
correct date Asana should spit out: 12/31/26

The problem: Asana isn’t issuing the correct dates.
In the above example, its issuing out 10/30/26

Has anyone encountered this and has an easy solve?

Hi @Jay_DeThomas1 , I take it your WBO is a formula field?

Would you mind sharing a screenshot so we can see if we can help you out?

Note, the ‘Due date’ input which is available in a Formula field is the Due date of the particular task, not the project Due date.

This has been resolved. The issue was a second hidden menu that has a checked box defaulted to “skip weekends” which was throwing all of our projects off. Unsure why Asana hides this as it relates to dates.