Due date calculations of number of days from start date not working when template is made into a project

I have a project template where every task is dependent and the due dates are based on specific days added to the start date. I’m not skipping weekends. I have several tasks are scheduled for 240 days out from the start date, but when I create the project from the template the due date is always set to “Tomorrow”. It is like Asana does not even see the task due date logic. Looking at forum history this has been an issue for years, but I would have thought this bug would have been squashed by now. Any suggestions?

This doesn’t sound like a familiar bug that I can recall; can you provide links to the places in the forum where it’s discussed? Thanks!

1 Like

@Dana_Hagen,

That other thread was a different issue than you’re describing, and was not a bug - he just needed to turn off the Skip Weekends option.

Can you post a screenshot of your template and one of the resulting project, so we can see the issue “in person”?