Sub Task Auto Trigger

At the sub-task level, is there a way to set a sub-task due date field to either provide a notification and/or update a task/project status flag AUTOMATICALLY when the sub task goes into a past due status at the stroke of midnight? We currently have the premium plan and would like to know if this capability exists and if so, how to configure it. Currently we MANUALLY change the status flag at the project level and task level to ‘behind schedule’ when a sub-task becomes past due but would like to see if this can be performed AUTOMATICALLY without having to rely on team to constantly monitor and manually update.

1 Like

You can now use rules to run on subtasks and main tasks - when due date is approaching, add comment (so it flags)