setting up rule

I have under My Tasks severtal rules like moving tasks to a certain section when certain due dates are met.

Ex: I have a task changed to 1. apr. Thats a week from now. However the task is set to “due today/do today” from the rule I have set up. How can this be automatically changed when I change an due date?
Hope this was understandable. If not I will try once more.


CleanShot 2025-03-24 at 15.41.32@2x

1 Like

Hello @Rune_Haarberg

In theory, the rule should work.
So either there is an issue with the rule itself, or you might have other conflicting rules that stopping this one from playing.

Will you be able to share the rules - without revealing confidential info?

1 Like





1 Like

Due date rules only run once a day at / around midnight.
So changing the due date will not trigger the rule.

3 Likes

Ah! I totally forgot about this! Thanks @Herve_Buisset
You came to the rescue :slight_smile:

@Rune_Haarberg Hope this helps!

2 Likes

That occured to me.
Thanks.

1 Like

@Rune_Haarberg FYI our Flowsana date-based rule triggers evaluate immediately when a task date changes, not just at midnight.

2 Likes

This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.