How can I set a subtask due date relative to the due date of the parent task that runs WHEN the parent task is created? I set up the following rule, but the subtask due dates don’t actually get assigned.
Here’s a screenshot of the rule with the relative due date task open:
Here is the same screenshot but showing all the subtasks it’s supposed to populate. You can see that they all have a relative due date rule set for them:
When I reached out to Asana support, they replied with the following:
"Reviewing the parent task and subtask, I can confirm that what you’re experiencing is expected behavior. This is because the due date must already be set on the parent task before the rule begins to run. Otherwise, the subtask’s due date will not populate. So if the rule starts to run before a due date is assigned, the subtask will not inherit a due date.
In this case, you may need to either manually set the due date on your subtask, restructure your existing rule, or create a new rule to ensure a due date is added to your subtask."
Can anyone advise me on how to accomplish having subtasks populate the relative due dates correctly?