Issue: Project Baseline is great but there is one glaring issue. If you make no changes to schedule for any length of time and you want to go back to find the last time there was a change to schedule you litterally have to go a click every single day until you find the day that there was a change in schedule.
Proposed Fix: Because there is a snapshot done everyday to the baseline the calendar you use to choose a date to set baseline should only show days where there was an actual change to the schedule, the days where there was no change should be greyed out and not selectable since there was no change and days you revised the schedule should show up. That way if there is long stretches of no changes (which is normal) you only have to check the days where something was done so you can go see what that change was.