Hi,
When scheduling our projects, majority of our tasks have dependencies. However, if I schedule task A on a particular day (eg. 1.1.20) and Task B (with a dependency on Task A) is also scheduled on 1.1.20 the dependencies are marked red. If the date of Task A changes to 3.3.2020, then Task B stays at 1.1.2020
Am I missing something here? Shouldn’t all tasts that are dependent on each other move together? Eg if Task A moves 3 days, then so will Task B as they are dependent on each other?