Hi all-
I’m building a new (physical) product development project template in Asana, and I’m having issues with the auto-shifting of dates.
Issue: Dependent Tasks are not date shifting to new dates.
Example: Task 1 shifts to end on 3/7/25. Task 2 (FS) should then start on 3/8/25.
Observations: the shifted task moves in the Gantt chart, but none of the dependent tasks do.
Notes: many tasks overlap, or are managed concurrently, sometimes I will need to adjust durations and dates that impact multiple tasks.
Any thoughts?