Reporting: Complete & Incomplete tasks

Trying to do an Advanced Search so I can get a report to see complete tasks for the past 7 days and incomplete tasks for the upcoming 7 days. I’ve tried several different scenarios but it seems to only pull in either completed or incomplete tasks and I’m using the Any option.

What should I be choosing for the Completion field and should I be having to use any filters to get the information I want?

Thanks!

Welcome @hkellerman! Do I understand correctly that you want to setup one report to to both searches?
I would recommend creating two different reports.

  1. One with Completion set to “Complete” & Due date set to “Within the last 7 days”
  2. The other one with Completion set to “Incomplete” & Due date set to “Within the next 7 days”

Hope this helps

1 Like