Hi,
Currently when creating templates, Due Dates can only be set from cascading after project start date or leading up to project Due Date. There are certain tasks that need to happen in the templates that I create during pre-launch but the launch date can sometimes fluctuate and therefore can’t be categorised as XX days after project start date and it’s also not the final project due date. Is it possible to have XX days after linked to Dependencies so that these dates are automated as soon as a Launch Day is confirmed?