Hi @Jasmin_Schiener , welcome to the forum
This can actually be ‘visually’ achieved (not technically achieved) with the following workaround, which requires any paid version of Asana:
-
Create a multi-select type field and populate all the options with the names of all your sections.
-
Select tasks in each section and set the value of the multi-select to be the same.
-
Set additional multi-select options for tasks that you want to appear in more than one ‘section’.
-
Optionally (but recommended), delete all your sections but keep all tasks (first choice in the delete section popup) **note below…
-
Along the top left of your list view, set the ‘Group by’ button to your multi-select field.
You should now see your list view appear as before, but with those specific tasks appear in more than one section.
** if you have any rules based on your ‘real’ sections, pause them BEFORE you deleted your sections - then edit your rules and base them on your multi-select field rather than the ‘real’ sections.