Thanks for suggestion! But it’s still not what we’re looking for. In the solution you suggested - there are not displayed incompleted tasks. We would like to see:
- tasks sorted by assignee
- completed within last 24 hours
- all incompleted
I was possible with the previous view filters. Now it’s not…
Regarding our workflow. We imitate Jira software. We’re doing basically the same thing as a regular scrum in Jira.
We’ve also started to build our own burn down chart for asana, as there’s none yet (here’s the topic: SCRUM: Creating a burn down charts using custom fields)
The screenshot of the scrum project I posted earlier - we use it as… well… a scrum It’s convenient to sort tasks by assignee, cos the everyone can use the project to see his/her scrum tasks at one place (not mixed tasks assigned to whoever else). And tasks of others as well. It’s a great way to see what everyone doing, done and will be doing at one place.