Hello, we use a project board for our large scale projects and have relevant team members constrained within the board. Each team member is assigned their own column with workload.
Can I give an arbitrary number to each of their assigned cards WIP so that we can’t give them more than their workload capacity?
For Example, Jeff has 5 cards under his name column in Asana. One card counts as 5 workload points, another card counts as 2 workload points and the final three cards are 3 workload points a piece. Adding another card under the “Jeff” column would put his workload points over 10+ and not allowed.
When Jeff completes a task, workload points will be deducted from his overall x/10 total.
Is this possible in Asana through fields or something that I’m missing?