In project or task templates, I would love to see an option to calculate due dates based on estimated duration or effort. For example,
- Project Start Date is November 1st.
*Task 1 takes 3 days to complete
*Task 2 takes 4 days to complete
*Task 3 takes 5 days to complete.
The tasks should have these completion dates:
*Task 1 is due November 3rd
*Task 2 is due on November 7th
*Task 3 is due on November 12th
This should also take into account task dependencies if established.