Dependencies do not import correctly from CSV files

Dependencies were added as a field in CSV files exported from projects. Discussion on that here.

However, if that CSV is then imported into another Asana project- the tasks do not link correctly and instead additional columns are added into the project which simply list the names of tasks that a particular task is dependent on. If a task is selected, the dependencies section of the task information is blank.

Suggestion is that tasks that are linked in a project that is exported to csv and then that csv is imported into another project- the links remain as per the initial project.

Hope that makes sense?

@Alex_Thomas,

I believe these two references will allow you to import as you desire:

This would be easier if Asana on export used the expected column name for import, so Iā€™ll leave the request here; donā€™t forget to add your vote at the top.

Larry

1 Like