Dashboard Filter Task Completion Status Bug

Briefly describe (1-2 sentences) the Bug you’re experiencing:
Task Count Chart created with two filters:

  1. Task Completion Status: Incomplete
    Status (Custom Field): Delayed

Chart ignores the task completion status filter and counts all tasks with custom Status “Delayed”

Steps to reproduce: As above

Browser version: Using Asana desktop application, MS Windows 64 bit.

Upload screenshots below:

And the chart in the dashboard was correct?

Chart in dashboard was incorrect. Displayed task count of 5.
image

Hi @Kieran_Naylor, thanks for flagging this!

I’ve gone ahead and escalated this to our Product team. I’ll keep you posted and let you know as soon as I have an update :slight_smile:

1 Like

As an update: I have noticed that this is occurring on multiple projects that use the same custom template. I also have a “rule” in place that changes the custom field “Status” based on approaching the due date and passing the due date. It appears that the majority of these miscounts were processed through this rule recently. Not sure if that helps or not.

Hi @Kieran_Naylor, thanks for your patience here :slight_smile:

Our Product team has confirmed that bug should now be fixed. Let me know if you’re still running into issues :slight_smile:

1 Like

Thank you so much!

1 Like