Workload question, how to show hours by section instead of assignee?

I’m trying to use the Workload option.

I have a project that has 6 sections. Each Project section basically represents a department on our production floor. They are NOT assigned to individual people and I’m not about to junk up my department manager’s My-Task lists by assigning all those tasks to each department manager.

Is there a way I can get the Workload to display daily Estimated Time by Section instead of Assignee?

If so, this would be marvelous but I cannot find how to do this.

That would be a dashboard in your case

I’ll look into that. I already have a sizeable dashboard for this project and I don’t seem to be able to create a second dashboard tab that I could name “Departmental Dashboard”, so I’ll have to add these graphs to the bottom of the screen. Visually messy but at least it will work. Thanks!

Yes indeed you can’t have multiple dashboards (yet?)