I want a notification whenever the due date for a project has been changed.
I also want to be able to track whenever this happens, over time.
I tried setting up a rule that triggers when the date is changed and the due date is not empty, but I do not see any appropriate “Do this” that would allow me to know if the date was changed and how to track changes overtime.
I would prefer to use Portfolio rules as each department is represented by a Portfolio and their projects throughout the year are added to their specific portfolio.
So I would want to get a notification (or something like a task being created somewhere, or comment, etc) whenever a due date for a project is changed.
And it would apply to all projects added to the portfolio over time.
I showed three potential actions you could take, and the menu of other ones. You’ll have to decide which one(s) might work for you for your notification; none do exactly what you want, though; maybe one day.
Another option:
If you were to keep the project start/due date in a task in the project, then you could use this solution: