You have a project start date and a project end date.
There are 35 weeks’ of tasks that need to be accomplished by the project end date.
No problem. You set a start date and end date, create the tasks and you can see that on a timeline.
What happens with slippage?
How do I track actuals versus when tasks actually get delivered?
It’s week 6 in the project in actual time, so up to week 6’s tasks should be complete, but I look and see, even though it’s week 6, I can see only up to week 4’s tasks have been done, so we’re 2 weeks behind. How do I track that with Asana or any Asana integrations?
It’s very easy to track this manually for one project.
Now imagine you have 60 projects with different start and end dates.
I need to be able to see actuals versus predicted dates for all tasks in an easy visual way.
How do I do that please?