I’m looking for the best way and feedback/work arounds to solve for:
- Auto populate the due date of a parent task based off the last subtask. Currently isn’t working and the last subtask IS a dependency blocking the parent task
- Task templates appear to NOT have the capability to use anything other than the task creation date for the due dates of subtasks and the subtask rule has a limitation of 20 subtasks per rule logic and then the last subtask in each is unable to be a dependency for the first subtask in the next group of subtasks.
- Shift FORWARD due dates as dependent subtasks are completed.
Goal is to have 38 subtasks added to a parent task with due dates being based off various SLAs and assignees.