Is there a possibility to make a rule, to assign responsible into subtask? Now, the rule creates the whole section with responsibles. It appears at the bottom of the main task. We need to assign into tasks/subtasks of the main template, without creating additional tasks.
Hi @Volodymyr_Lapovets and thanks for that question,
Yes, and no…
If this option is selected (see screenshot below), the rule will apply also on the subtasks
However, the trigger needs to happen on the subtask (the rule is not “cross-level” : task > subtask)
Hope that could help, please let me know