Resource management vs capacity management (same or different?)

Hi,

I’m testing the free trial at the moment but the functionality that is a deal breaker for us is not available. What I need is capacity management as described here: https://help.asana.com/hc/en-us/articles/22337928424859-Capacity-planning#:~:text=To%20create%20an%20allocation%2C%20simply,entire%20allocation%20when%20plans%20change

The article mentions that capacity management is only available in Enterprise.

Does someone know if this is the same as “Resource management” available in both Advanced and Enterprise? I don’t see anything called “Capacity management” under Enterprise so I’m confused.

Thank you,

Julie

Hi @Julie_Demers,

Welcome to the forum!

I’ve moved this topic to Tips and Tricks as this more a question than it is a feature request.

I’m not sure what is meant with resource management and where this was mentioned, but it is safe to assume it isn’t the same as the article you linked.

You’re right, thank you!

I see Resource management as a listed feature in this page: https://app.asana.com/0/billing/pricing/1207833109773506

I get the French version automatically so Gestion des ressources but hopefully you can see the English version.

See Portfolio workload and Universal workload

Portfolio workload seems to be the one available in the advanced plan.