Relative due dates in custom project templates

Hello,
Am I correct that this is not available to tasks that are created via rules within the template?

It seems as though I the before/after drop down is available in the tasks built into the templates initially, but when creating a rule that creates a new task I still only have the option to enter a positive integer, i.e. X days “after the trigger task is due.”

I’d like to be able to set the new task to have a due date of X days before the Project Due Date.

Am I missing a way to do this?

Thanks
Zhana

Hi @Zhana_Morris,

I think you are correct. This applies to tasks that are in the project template.

This means that it works for tasks that are already in the template, not tasks that are added later by rules.

Thank you.

I’m afraid you’re not missing anything, @Zhana_Morris

Consider voting with the purple button at the top of this thread, if it’s what would help you, or maybe you can find another thread, or add the request in Product Feedback if not already there:

Thanks,

Larry