In the process of revamping how we display and access all our jobs, and track them through design to install.
One of the crucial elements we assumed we could do was filter all these jobs by Assignee, and then expand their subtask list in Gantt view.
Unfortunately, the moment I sort by Assignee, the option to expand the subtask list disappears, which to be honest is going to really make a huge mess out of this project, because we have about 15 different possible assignees, and every one of them is going to NEED to be able to see only their tasks, expanded, on Gantt view.
First image, sorted by assignee. No “carrot” for expanding the subtasks despite having plenty of room for it.
Second image, not sorted, but the carrot is there, and can be expanded.